Yacht Club Project Update

Weekly Update

Week of: 2 Dec – 6 December 2013

  • 2nd floor wall sheathing 98% complete.
  • Trusses are  set 99% complete
  • Filling dirt for paver area and spread  back area of project
  • Roof sheathing Inspection Passed- 3rd party inspection
  • Plumbing Rough – In 50%
  • Started roof paper/Shingles schedule for delivery
  • Exterior windows and doors scheduled for delivery