YC Project Update

IMG_4864

Work Completed :

  • Tower papered
  • Gas line rough-in  99%
  • Mechanical – 94%
  • Mason 65% Complete)
  • Drywall Hanging Tower Complete
  • Drywall finishing  (Taped)
  • Permanent Power Complete
  • Finishing drywall 1st   floor 99% & 2nd floor 90%
  • Started Kitchen Make up air 90%
  • HVAC units on site (Attic Set) 85%
  • HVAC lines installed 90%
  • 2nd floor bathroom floor Complete
  • 2nd  floor bathroom wall tile Complete
  • 1st floor kitchen floor tile 100 % Complete
  • 2nd floor kitchen epoxy floor 100%
  • Painted door frames 80%
  • Painted walls 75%
  • Fire Marshall Hydro 100%
  • Tower insulation inspection complete
  • Tower Window 100%
  • Exterior decks South 98%/West 95%
  • Trim Stain – 60%
  • Trim 2nd floor Dining  30%
  • ACT Grid-75%
  • Electrical Trim – 40%
  • Cupola Drywall complete