Yacht Club Project Update

YC-10

 

 

 

Weekly Update, Week of: 9-14 December 2013

Work Completed this Week:

  • 2nd floor wall sheathing 98% complete.
  • Trusses are  set 99% complete
  • Roof Paper complete 40%
  • Roof sheathing Inspection Passed- 3rd party inspection
  • Plumbing Rough – In 65%
  • Electrical 20%
  • Tyvek wall covering 60%Aerial Photo taken by Mike Adelman, 11 Dec 2013