Yacht Club Project

IMG_4519

 

Update

Work Completed this Week (27-31 Jan):

  • Tower Framed/Sheathing 90%
  • Tower Trusses Set
  • Plumbing Rough – In 98%
  • Mechanical – 55%
  • Electrical Rough-In 98% (Interior)
  • Pipe Insulation 90% Complete
  • 1st  & 2nd Floor Insulation Complete and Inspected
  • Mason 65% Complete
  • Rough-In Security System 1st & 2nd floor 90%
  • Drywall Hanging 99% complete 1st floor/75% 2nd floor
  • Electrical Panels being set
  • Colm. Framing 80% complete
  • Bulkhead Framing 90% complete
  • Installing Steps to Attic HVAC Room
  • Finishing drywall 1st floor (50%)
  • Started Kitchen Hood installation 1st floor

 

 