Yacht Club Project Update

Week of: 11 – 15 November 2013

 

  • 2nd floor wall framing 95% complete.
  • 2nd floor wall sheathing 30% complete.
  • Trusses prepped began setting Friday (Nov. 15th)
  • Set floor joists on 2nd floor above Harbor Master shop.

 