Work Completed :

  • Trim 1st floor 40%
  • Mechanical – 99%
  • Mason 99% (Complete)
  • Tiki Bar/Masonry 100%
  • Tiki Bar Rough-in 100%
  • HVAC units on site (Attic Set) 99%
  • HVAC lines installed 99%
  • Painted walls 99% 2nd floor—1st floor 50%
  • Exterior Trim/siding/50%
  • Trim 1st floor Dining 80%
  • ACT Grid-100%
  • Electrical Trim – 85%
  • Metal Roof – 85%
  • Lights install 80%
  • 1st floor flooring 90%
  • Hardwood floor 2nd floor dining 75%
  • Grading/Pavers 55%
  • Drywall tower area 75%
  • Passenger Elevator 40%
  • Service Elevator 10%
  • Kitchen Equipment 80%
  • Cooler/Freezers 80%
  • Rest Room Fixtures 40%

 