Yacht Club Project Update

20140223_141136

Work Completed this Week (17-21 Feb):

  • Tower papered
  • Plumbing Rough – In 100%
  • Gas line Rough – In 90%
  • Mechanical – 90%
  • Electrical Rough – In 99% (Interior)
  • Insulation Cupalo – 2nd floor bar complete
  • Mason 65% complete
  • Drywall Hanging Tower Start Friday
  • Electrical Panels Set
  • Finishing Drywall 1st 85% 2nd floor 80%
  • Started Kitchen Make up air 50%
  • HVAC units on site (attic set) 85%
  • HVAC lines installed 85%
  • 2nd floor bathroom floor tile 90%
  • 2nd floor bathroom wall tile 90%
  • 1st floor kitchen floor tile 99%
  • 2nd floor kitchen epoxy floor – curing time 72 hours
  • Painted door frames 60%
  • Painted walls 60%
  • Fire Marshall Hydro 99%
  • Tower insulation inspection today
  • Tower window 100%
  • Exterior decks South 90% / West 60%