Yacht Club Project Update

Week of:  2/3/14 through 2/7/14

 

  • Tower sheathing complete
  • Plumbing Rough – In 100%
  • Gas line rough-in  70%
  • Mechanical – 85%
  • Electrical Rough-In 99% (Interior)
  • Pipe Insulation Complete
  • Insulation  Cupalo -2nd floor bar complete
  • Mason 65% Complete
  • Rough-In Security System 1st & 2nd floor 100%
  • Drywall Hanging 99% complete 1st floor/95% 2nd floor
  • Electrical Panels being set
  • Colm. Framing 100% complete
  • Bulkhead Framing 100% complete
  • Finishing drywall 1st  85% & 2nd floor (60%)
  • Started Kitchen Hood  1st & 2nd floor installed
  • Spray insulated Steel Beam
  • HVAC units on site (Attic Set) 80%
  • HVAC lines installed 80%
  • 1st floor bathroom floor tile installed
  • 1st floor bathroom wall tile 90%
  • 1st floor kitchen floor tile 95%
  • RC Channel 2nd floor dining complete
  • Doors and windows stained and sealed 100%
  • Painted door frames 60%
  • Painted walls 60%
  • Fire Marshall Hydro 95%
  • Tower framing inspection complete
  • Tower Window 95%