Yacht Club Project Update

IMG_4584

Week of:  1/13/14 through 1/17/14

  • Tyvek 100% complete.
  • Cupola complete
  • Plumbing Rough – In 85%
  • 1st Floor Plumbing Rough-In Complete
  • Mechanical – Installation in Progress
  • Electrical Rough-In 80%
  • 1st Floor Electrical Rough-In /Complete (Passed)
  • 1st Floor Framing Inspection/Complete  (Passed)
  • Shingles 90% complete
  • Exterior windows, doors 95% Complete
  • Mason 55% Complete
  • Kitchen equipment field layout Complete (Good)
  • Rough-In Security System 1st floor
  • Rough-In Fire Alarm System

 