Yacht Club Project Update

DSC_0093

Weekly Update, Week of: 23-27 December 2013
Work Completed this Week:

  • Tyvek 90% complete.
  • Cupola complete tomorrow
  • Wall sheathing passed 3rd party inspection
  • Plumbing Rough – In 75%
  • Electrical 60%
  • Shingles being installed
  • Kitchen vent roof curbs installed
  • Exterior windows, doors being installed
  • Mason 50%
  • Started framing Tower

 