Yacht Club Project Update

 


 

Week of: 25 – 29 November 2013

 

  • 2nd floor wall framing 99% complete.
  • 2nd floor wall sheathing 95% complete.
  • Trusses are being set 98% complete/progress slowed down due to heavy winds Mon. –Tues. –  Rain Wed. – Holiday Thurs. —
  • Paver area and spread back area of project underway (fill dirt)
  • Wall sheathing Inspection Passed- 3rd party inspection passed also
  • Plumbing Rough – In 40% complete

 