Yacht Club Project Update

Work Completed this Week (18 – 22 Nov):

  • 2nd floor wall framing 99% complete.
  • 2nd floor wall sheathing 80% complete.
  • Trusses are being set 80% complete/progress slowed down due to heavy winds Mon. through Wed.
  • Goodhill hauling in fill for paver area
  • Wall sheathing Inspection Today (Nov 22)
  • Plumbing Rough – In 20%