Yacht Club Project Update

Work Completed this Week (28 Oct – 1 Nov 2013):

  • First floor framing 100% complete.
  • Floor joists 75 % complete (2nd floor).
  • Floor sheathing 50% complete (2nd floor).
  • 2nd floor north wall 100% framed.
  • Marina retaining wall 90% complete.
  • All trusses delivered on site (except additional trusses required to support 2nd floor curtain walls). 

Work Completed this Week (21-25 Oct 2013)

  • First floor framing approximately 98% complete.
  • Steel set for building approximately 99% complete to be complete Monday (Oct. 28th).
  • Started setting block for Marina retaining wall.
  • Elevator shafts complete.
  • Hoist beams installed for both elevators.
  • Began preparing floor joists for installation (2nd floor).
  • 1st floor sheathing 98% complete.
  • Floor diamonds (concrete around steel beams) poured.

Work Completed this Week (14 -18 Oct 2013)

  • First floor framing approximately 85% complete.
  • Steel set for building approximately 99% complete (waiting for elevator shaft block to be complete).
  • Marina retaining wall footers poured.
  • Elevator shaft block 75% complete.

Work Completed this Week (7-11 Oct 2013)

  • The swale is complete N/E side of pool parking.
  • Framing layout is 90% complete.
  • Framing top and bottom plates are cut; 50% of the bottom plates attached.
  • Mason has started elevator walls.
  • The steel delivery has been rescheduled for Monday morning due to weather.
  • The steel erector is also scheduled to start Monday morning.
  • The column leveling plates have been set and grouted.
  • The entry and dinning porch pads were canceled for today (County inspection Complete) due to weather & will be poured Monday or Tuesday next week.
  • Retaining wall footer was canceled for this week due to weather/will rescheduled for next week.
  • Steel will be set next week.
  • Framing will continue next week.
  • Mason will complete elevator walls next week & Start retaining wall.