Yacht Club Project Update

Week of: 4 – 8 November 2013

 

  • Finished floor joists & floor sheathing (2nd floor).
  • Start 2nd floor wall framing (approximately 50% complete).
  • Finished marina retaining wall.
  • Started facing on 1st floor exterior (approximately 25% complete).
  • Completed fire & domestic water hook up to building; conducted & passed County Fire Marshall Hydro-Flow Pressure Test on Wednesday (Nov. 6th).