Projects

Projects in the Pines (presented by Colby Phillips):

March 18-24, 2019

The Public Works team met with a few homeowners last week to discuss drainage issues going forward.  We will be holding a working group on this issue Friday, March 22 at 10am at the Public Works office if anyone would like to attend.

We will be leveling the bids for the Country Club and Police Department today at which time the Board will then make its decision.

Andre Jordan, our golf course superintendent,will be ordering and planting Bermuda seeds for our Huntington Park fields.  This should bring in some nice turf by late spring, early summer.

The team met with the insurance company last week to bring our policy up to date.

The old staging area at Swim and Racquet Club has had all the stone/gravel removed and a new split rail fence put up. The sod will be going in this week.

The second floor of the Beach Club is currently being painted and we are looking to put in a ADA-compliant sidewalk to the bathrooms in the next few weeks.

Nobie Violante is currently working on updating our Bulkhead plan schedules going forward.  We will be creating a study with pictures.

Just as a final reminder, we have our Second Annual Community-Wide Job Fair this Saturday at the Community Center from 9am-12pm.

Recreation Manager Debbie Donahue is currently working on the White Horse Park replacement project. We are excited about what this project will bring to the community, especially our children and young at heart!

Have a great week and thank you all for your continued support of the Ocean Pines team!

 

 

Ocean Pines is constantly improving its facilities and amenities. Take a look at some of the new, existing and completed projects below:

Current Projects

  • Golf Club

    The Association and its Board of Directors are working to get bids on the Golf Club renovation project to the second floor. Continue reading


 

Completed Projects

  • Two New Platform Tennis Courts 2017

    Work has begun on the two new platform tennis courts at the Manklin Meadows Racquet Sports Complex! Excitement grows as the Ocean Pines Association begins an expansion project at the Manklin Meadows Racquet Sports Complex this week. A proposal of two … Continue reading

  • Community Center Gym Floor Replacement

    The Community Center Gym floor has been replaced. The gymnasium was reopened Wednesday, January 18.  

  • Manklin Meadows Playground

    River Valley Recreation has completed the playground installation project at the Manklin Meadows Park in south Ocean Pines. ... Continue reading
  • Bridge Repair

    Board Approval Date: April 28, 2016 Projected End Date: April 17, 2017 Construction is still underway. On the Clubhouse Bridge project, we are 97% complete. ... Continue reading
  • Huntington Park 2016

    Board Approval Date: August 2016

    Progress is being made in the Huntington Park project. The park, located on Birdnest Drive, now features a new playground. Continue reading

  • White Horse Park New Bathrooms 2016

    Board Approval Date: May 27, 2016 Project Start Date: September 2016 Projected End Date: February 1, 2017 New construction of a stand-alone bathhouse in White Horse Park, which began in September 2016, has been completed. ... Continue reading
  • Outdoor Pickleball Courts 2016

    Board Approval Date: May 26, 2016 Tennis Courts #11 and #12 will be re-purposed to accommodate eight new permanent Pickleball Courts at Manklin Meadows Complex. ... Continue reading
  • Beach Club Bathroom Renovation 2016

    Project Start Date: March 6, 2016 Projected End Date: May 11, 2017 Renovations are underway to the Ocean Pines Beach Club bathrooms ... Continue reading
  • Sports Core Pool Renovation 2016

    Board Approval Date: February 25, 2016 Project Start Date: July 10, 2016 Projected End Date: September 10, 2016

    The Sports Core Indoor Pool will receive a renovation of the pool and the deck area and will receive some enhancements that will make this facility’s experience a lot better. Stay tuned as we update this page with the progress. Continue reading

  • Mumford’s Landing Pool and Deck 2015

    Board Approval Date: March 28, 2015 Project Start Date: April 1, 2015 Projected End Date: May 23, 2015 RFP responses included different approaches to the repair of excessive pool cracking and settlement at one pool corner. View the Pool repair and replacement analysis. Board approved to repair using a new pool liner technology seen in the report. ... Continue reading
  • Marina Fuel Pump Replacement 2014

    Project Start Date: January 5, 2015 Projected End Date: April 30, 2015

    Ocean Pines Marina will receive new gas pumps for fueling boats at the marina dock station located at Mumford’s Landing and near the Ocean Pines Yacht Club. Continue reading

  • Swim and Racquet Pool Resurfacing 2015

    Project Start Date: January 5, 2015 Projected End Date: May 15, 2015

    Pools and Spa are currently working on the Swim and Racquet Club Pool to resurface the bottom where the plastering had been peeling off the last few years. Continue reading

  • Golf Course Greens Project 2013

    Completed May 2013. If you have not visited, you should reserve a tee time at the Ocean Pines Golf and Country Club in Ocean Pines, MD. Managed by Billy Casper Golf, the community took on a project to renovate all 18 greens. The course looks spectacular. Open to the public with memberships available. 410-641-6057 or visit www.oceanpinesgolf.org Continue reading

  • White Horse Park Boat Ramps Replacement 2014

    Board Approval Date: September 27, 2014 Project Start Date: January 1, 2015 Projected End Date: April 15, 2015

    Fisher Marine began the project in January 2015 and the Boat Ramps will continue to be closed during construction. This project replaces the existing boat ramps and piers in White Horse Park off Beauchamp Road in Ocean Pines. Project includes: the replacement of the two existing boat ramps; replacement of 3 existing piers with one new pier and a temporary berthing dock (for boats waiting to use the ramps); installation of a new vinyl bulkhead and the construction of a concrete pier with a gangway and floating dock. Continue reading

  • Marina Gas Tanks Relocation 2013

    The fuel tanks had to be relocated when we started construction on the new Yacht Club facility. The old tank structure was demolished, tanks relocated, tanks refilled, the final piping and electrical work were completed. We erected a new temporary Marina Building at the end of the dock and made final preparations for fuel sales by August 2013.
    Continue reading

  • New Yacht Club Pool 2013

    A new pool was constructed at the Yacht Club Facility just before and sometimes during the construction of the new Yacht Club facility. Some of the construction photos can be seen on the Yacht Club Project page. The pool is pretty much the same foot print as the original pool and not quite as deep. A ribbon cutting for the new pool was held on August 8, 2013. Continue reading

  • New Yacht Club Facility 2013

    Project Updates Project Galleries Important Links Referendum 07 August 2012 referendum materials mailed to all eligible property owners. 07 September 2012 referendum resulted in a majority of votes of YES! From the 7,698 property owners who are eligible to vote, … Continue reading