Hingham Lane Update

hingham 1

 

 

 

 

 

  • Installed discharge pipe into the existing junction box (which contains the double barrel discharge under Ocean Parkway).
  • Crossed first driveway moving towards Hingham Lane and installed two catch basins to aid in drainage in this area.
  • Installed first junction box on the north side of Hingham Lane.
  • Encountered an electric line that was 35′ off the Choptank mark from Miss Utility – Choptank has spliced and provided slack to work around it.
  • Will continue working on installing pipe on Hingham Lane.
  • Will work Thanksgiving week Monday through Wednesday and possibly Friday and Saturday.
  • If no major issues occur, work should be complete on or around December 6th.